Four lifting stations in Dora – Baghdad
- Constructing concrete pits.
- Installing new pumps.
- Installing new electrical boards.
- Installing new piping.
Construction of two gray water-lifting stations in Heet Town, Anbar Governorate
- Constructing the stations on two open gray water channels.
- Installing all mechanical and electrical fittings including pumps.
- Laying 2,400 meters of main pipes for storm water, complete with gullies.
- Lowering, cleaning, re-sloping and constructing culverts along 4,400 meters of open gray water channels.
Construction of one gray water lifting station in Shatra, Thiqar Governorate
- Constructing the station installing all mechanical and electrical fittings including pumps.
- Laying 1,200 meters of main pipes for storm water evacuation.
Overhauling four sewage lifting stations in Hai Town, Wasit Governorate.
Constructing a gray water/sewage lifting station and 1150 meters of gray water pipeline in Afak, Qadisseyah Governorate
Constructing a gray water/sewage lifting station and laying 2,000 meters of 600 meters diameter storm water pipeline in Beled Ruz, Diyala Governorate.
Constructing lifting stations, and re-sloping and cleaning 900 meters of open gray water channels in Muqdadiyah Town in Diyala Governorate.
Rehabilitation of Al-Khalis Sewage Lifting Station in Diyala Governorate.
Rehabilitation of Sewage Treatment Compact Unit at the Pediatric Hospital in Hilla, Babel Governorate.
Potable water network
749.5 kilometers of potable water network was laid in twenty-two towns in central and southern Iraq.
Work included assessments, design of new network, laying the network, connecting the network to beneficiaries, both households, government buildings, and commercial sites, and making good the pavements and roads once the work had been completed. |